Bemax completes Vrulja-Mijakovići road ahead of schedule; Ivanović: Important section for Pljevlja, works on open route and bridges are being carried out in parallel | Zvanični sajt kompanije Bemax Zvanični sajt kompanije Bemax

Our

News

We are Bemax

Bemax completes Vrulja-Mijakovići road ahead of schedule; Ivanović: Important section for Pljevlja, works on open route and bridges are being carried out in parallel

The section will be completed about 20 days ahead of schedule.

The works on the Vrulja – Mijakovići road section will be completed before the legal deadline, announced the engineer of the Bemax company, Nemanja Ivanović.

He pointed out that the works on the open route and on the bridges are being carried out in parallel at the Vrulja – Mijakovići construction site.

Earlier today, the first layer of asphalt was completed on bridge number 1, while works on bridge number 2 are in the final phase.

“We expect to complete the asphalt on bridge number 2 in the next two days. The remaining works are the production of horizontal and vertical signalization, cleaning and tidying up the construction site,” emphasized Ivanović.

The Bemax company will, as it announces, complete the works before the legal deadline.

“The official deadline for the completion of the works is December 20, but as you are used to from the Bemax company, this very important section of the road for the Municipality of Pljevlja will be handed over to the investor and citizens about 20 days before the deadline,” said Ivanović.

Let us remind you that the Vrulja – Mijakovići section is seven and a half kilometers long and connects the regional road Sljepač most – Trlica with the Pljevlja – Đurđevića Tara highway.