Works on the reconstruction of the main road M-2.4 Ulcinj – Sukobin

Execution of works on the reconstruction of the main road M-2.4 Ulcinj – Sukobin, section: Vladimir (intersection Ostros) – Sukobin, from km 65 + 055.78 to km 71 + 576.48

Execution of preparatory works, geodetic, works on the lower and upper machine, construction of tubular culverts Ø 1000 mm, L = 118 m, Ø 800 mm, L = 292 m and Ø 500 mm, L = 52 m, AB of retaining walls, reconstruction works 11 AB bridges, works on traffic signals and road equipment.

  • Route length: 6,52 km
  • Total excavations: 45.855,87 m3
  • Total embankment: 41.670,76 m3
  • Quantity of concrete works: 1.575,27 m3

Investor:

Direkcija za saobraćaj

Status:

Finished

Godina:

2011 – 2012

Value of contracted works:

3.000.000 €