Works on the construction of Willy Brant Boulevard
It is about the section from the intersection with Mosorska Street to the roundabout, i.e. the turn to the Autoput.
The length of the road: 600 m
- Earthworks – Excavation: 16.918,61 m3 – done 100%
- Earthworks – Embankment: 1.230,30 m3 m3 – done 100%
- Concrete and reinforced concrete works: 1.232 m3 – done 100%
- Asphalting works: 4.870,10 t – done 100%
Investor:
Uprava za saobraćaj
Status:
In progress
Year:
2022 – 2023
Value of contracted works:
1.500.000 €
It includes the execution of construction and construction-artisan works on the route, atmospheric sewage, water supply and installations of high and low current, the execution of electrotechnical works on installations of high current (public lighting, protection of 10kV cables, displacement and protection of LV lines and cable sewerage under the road) and performing geodetic works.