Works on the construction of the road MR1-II phase, section from Solila to Pržno
Construction of the road from Solil to the intersection for Pržno – II phase (from 6 + 600 to 8 + 780)
The length of the road: 2,12 km
Stepen izvršenosti objekta:
- Zemljani radovi – Iskop: 81.864 m3 – done 100%
- Additional earthworks – Excavation: 6.000 m3 – done 100%
- Earthworks – Embankment: 19.709 m3 – done 100%
- Additional earthworks – Embankment: 1.000 m3 – done 100%
- Concrete and reinforced concrete works: 952 m3 – done 100%
- Asphalt works: 5.157 t – done 100%
- Additional asphalt works: 310 t – done 100%
Investor:
Municipality of Tivat
Status:
Finished
Year:
2018 – 2019
Value of contracted works:
3.500.000 €