Works on the construction of the main road Risan-Žabljak, section tunnel Ivica-Motički Gaj
Works on the construction of the main road Risan-Žabljak, Section: entrance to the tunnel Ivica-Motički Gaj (km 3 + 090.50 – km 16 + 683.17)
Works on the construction of the main road and tunnel (L = 2.2 km). As part of this project, works were performed on: excavation in material from III to VI category (486,966.89 m³), construction of embankments from materials of all categories (291,896.39 m³), construction of bedding, execution of concrete and AB works, asphalt works , 19 t), installation of curbs, horizontal and vertical traffic signals and road equipment, hydraulic and electrical works, geodetic works.
- Route length: 13,59 km
- Total excavations: 475.723,89 m3
- Total embankment: 433.011,71 m3
- Quantity of concrete works: 27.490,57 m3
Investitor:
Porr Bau GmbH Beč d.s.d. Podgorica
Status:
Finished
Year:
2008 – 2011
Value of contracted works:
18.000.000 €