Works on the construction of the main city collector
- Earthworks – Excavation: 104.933 m3 – done 97%
- Earthworks – Embankment: 68.060 m3 – done 93%
- Concrete and reinforced concrete works: 1.480 m3 – done 95%
- Asphalt works: 3.376 t – done 100%
Investor:
Municipality of Podgorica
Status:
In progress
Year:
2020 –
Value of contracted works:
7.000.000 €
“Investing in a new wastewater treatment plant confirms that the capital Podgorica follows the Government’s development policies and provides conditions for further dynamic development. The capital is continuously developing a healthier and higher quality living environment, and the Government, for its part, will continue to contribute to its construction according to the needs of our citizens, “said Prime Minister Dusko Markovic.
As Mayor Ivan Vukovic said, the collector opens the preconditions for the long-term development of Podgorica and provides permanent protection of the Morača River, groundwater and water sources in the Skadar Lake basin.
The first phase, which includes complete works on the sewerage network, including the bridge crossing, as well as the main collector and the secondary one.