Works on the construction of Street 2 with accompanying infrastructure, the part located between zones K” and E” and D” and H”, in the scope of DUP Illino

The length of the road:

  • Earthworks – Excavation: 6.000,00 m3 – done 100%
  • Earthworks – Embankment: 2.141,00 m3 – done 100%
  • Concrete and reinforced concrete works: 217,00 m3 – done 100%
  • Asphalting works: 777,00 t – done 100%

Investor:

Municipality of Bar

Status:

Finished

Year:

2024 – 2025