Street construction works, Cetinje
The length of the road: 0,97km
Degree of completion of the object:
- Earthworks – Excavation: 20.895 m3 – done 100%
- Earthworks – Embankment: 10.921 m3 – done 100%
- Concrete and reinforced concrete works: 1.317 m3 done 100%
- Asphalt works: 2.169 t – done 100%
Investitor:
Direkcija za saobraćaj
Status:
Finished
Year:
2018
Value of contracted works:
500.000 €