Reconstruction works on the regional road R-20 (R-12), PHASE II-Berane-Podvade
Reconstruction of the regional road R-20 (R-12) Berane-Trpezi-Kalače, section Berane-Petnjica, PHASE II-Berane-Podvade
- The length of the road: 12.78 km
Degree of completion of the object:
- Earthworks – Excavation: 225.407 m3 – done 97%
- Earthworks – Embankment: 68.106 m3 – done 95%
- Concrete and reinforced concrete works: 5.246 m3 – done 95%
- Additional reinforced concrete works: 800 m3 – done 100%
- Additional reinforced concrete works: 300 m3 – done 100%
- Asphalt works: 36.887 t – done 80%
Investor:
Direkcija za saobraćaj Crne Gore
Status:
Finished
Year:
2018 – 2019
Value of contracted works:
7.000.000 €