Reconstruction od regional road M-2, section Ribarevina-Mojkovac

Reconstruction of the Main Road M-2 of the Ribarevina-Mojkovac, “Lepenac” site, construction of the third lane

Investor:

Ministry of Transport and Maritime Affairs

Status:

Finished

Year:

2017 – 2018

Total investment:

4.000.000 €

Length of the road: 7,6 km

Degree of execution of the project:

  • Earthworks – Excavation: 74,541 m3 – done 100%
  • Earthworks – Bulk: 49.560 m3 – done 100%
  • Concrete and reinforced concrete works: 8.173 m3 – 100%
  • Asphalt works: 20.294 t – done 100%

Construction and construction works on the route, AB supporting walls, AB mounting failures, AB semi-objects, drainage, traffic signalization and road equipment, as well as all geodetic works.

Additional works on the reconstruction of the main road M-2 Ribarevina-Mojkovac (support walls)

Degree of execution of the project:

  • Earthworks – Excavation: 10,387 m3 – done 100%
  • Earthworks – Bulk: 4.768 m3 – done 100%
  • Concrete and reinforced concrete works: 2.844 m3 – 100%