Highway Bar – Boljare

Investor:

Government of Montenegro, Ministry of Transport and Maritime Affairs

Status:

On-going

Year:

2015 –

Total investment:

141.000.000 €

DCIM100MEDIADJI_0091.JPG

Smokovac interchange

Total investment: 8.500.000 €
Start date: April 2019.
Deadline: 16,5 months
Degree of execution of the project:
Smokovac bridge: 19,41%
Overpass Zlatica: 59,45%
Underpass Mihaila Ivanovića: 67,60%
Under pass Dunavska street: 75%
Lane: 3%

Suka Tunnel

Total investment: 8.500.000 €
Start date: July 2017.
Deadline: 15 months
Tunel length, both lanes: 1.290,00 m
Degree of execution of the project:
Tunel excavation: completed 14.05.2018.
Concrete and reinforced concrete works: 100%
Tunnel drainage : 40%

DCIM100MEDIADJI_0023.JPG

Vežešnik Tunnel

Total investment: 27.500.000 €
Start date: April 2017.
Deadline: 21 month
Tunel length: 4.845,00 m
Degree of execution of the project:
Tunel excavation: completed 22.08.2018.
Concrete and reinforced concrete works: 98,73%
Tunnel drainage : 15%

Open lane (LK 0+000 – LK 6+440,00; RK 0+000 – RK 6+435)

Total investment: 13.000.000 €
Start date: December 2016.
Deadline:24 months
Route length: 4,56 km (lijeva i desna traka)
Excavations: 379.433,60 m3
Embankments: 693.593,57 m3
Degree of completion of the project:
Excavations: 78,86%
Embankments: 71,37%

DCIM100MEDIADJI_0033.JPG

Gornje Mrke bridge

Total investment: 4.500.000 €
Start date: December 2016.
Deadline: 24 months
Bridge length:
Left bridge: 296,00 m
Right bridge: 296,00 m
Degree of completion of the project: 91,75%

Mrke Tunnel

Total investment: 11.000.000 €
Start date: decembar 2016 godine
Deadline: 24 months
Tunel length: 1.583,00 metara
Degree of completion of the project:
Tunnel excavation: completed 15.12.2017.
Concrete and reinforced concrete works: 92,50 %
Tunnel drainage: 10%

Podsekcija 1.4. Concrete works

Total investment: 6.000.000 €
Start date: April 2017.
Deadline: 18 months
Route length: 4.042,16 m
Degree of completion of the project:
Support walls: length 336,00 m – degree of completion 100%
Drains: length 452,00 m – degree of completion 10%
Underpasses: length 185,80 m – degree of completion 100%
Lane drainage: 90%.

Overpass Preljubovica

Total investment: 500.000 €
Start date: August 2017.
Deadline: 10 months
Bridge length: 52,00 m
Degree of completion of the project: 82,78%

Overpass Kisjelica

Total investment: 500.000 €
Start date: October 2017.
Deadline: 10 months
Bridge length: 52,00 m
Degree of completion of the project: 88,38%

Pelev brijeg Bridge (part of Pelev brijeg interchange )

Total investment: 1.000.000 €
Start date: March 2018.
Deadline: 10 months
Bridge length: 100,00 m
Degree of completion of the project: 91,67%

Billing station and maintenance base

Total investment: 3.000.000 €
Start date: Jun 2019
Deadline: 24 months
Degree of completion of the project: 12%

Đurićev Laz Bridge

Total investment: 5.000.000 €
Start date: March 2017.
Deadline: 24 months
Bridge length:
Left bridge: 352,00 m
Right bridge: 324,00 m
Degree of completion of the project: 83,83%

Ratkov Laz Bridge

Total investment: 5.000.000 €
Start date: March 2017.
Deadline: 24 months
Bridge length:
Left bridge: 352,00 m
Right bridge: 324,00 m
Degree of completion of the project: 80,79%

Open lane (LK 17+311 – LK 19+305; RK 17+330 – RK 19+349)

Total investment: 7.000.000 €
Start date: March 2017.
Deadline: 24 months
Route length: 2,32 km (obije trake)
Excavations: 543.287,27 m3
Embankments: 386.113,00 m3
Degree of completion of the project:
Excavations: 83,20%
Embankments: 90,57%

Lutovo Bridge

Total investment: 3.000.000 €
Start date: March 2017.
Deadline: 24 months
Bridge length:
Left bridge: 212,00 m
Right bridge: 128,00 m
Degree of completion of the project: 56,50%

Vjeternik Tunnel

Total investment: 20.500.000 €
Start date: November 2016.
Deadline: 24 months
Tunel length, both lanes: 2.923,00 metara (half of the tunel we have been contracted for)
Degree of completion of the project:
Tunel excavation: completed 09.07.2018
Concrete and reinforced concrete work 88,88%
Tunnel drainage: 5%

Suvovara Bridge

Total investment: 5.000.000 €
Start date: July 2017.
Deadline: 18 months
Bridge length:
Left bridge: 184,00 m
Right bridge: 240,00 m
Degree of completion of the project: 92,11%

Open lane (LK 22+695 – LK 22+730; RK 22+570 – RK 22+735)

Total investment: 1.000.000 €
Start date: November 2016.
Deadline: 24 months
Route length: 203,00 m (both lanes)
Excavation: 26.672,02 m3
Embankments: 1.976,20 m3
Degree of completion of the project:
Excavations: 35,00%
Embankments: 0,00%

Krkor Bridge

Total investment: 9.500.000 €
Start date: July 2017.
Deadline: 22 months
Bridge length:
Left bridge: 334,00 m
Right bridge: 290,00 m
Degree of completion of the project: 73,84%

Open lane (LK 22+730 – LK 24+100; RK 22+735 – RK 24+140)

Total investment: 1.000.000 €
Start date: July 2017.
Deadline: 18 months
Route length: 1,73 km (both lanes)
Excavations: 404,482,35 m3
Embankments: 276.920,64 m3
Degree of completion of the project:
Excavation: 60,28%
Embankments: 75,67%

Concrete works are currently being carried out on the entire length of the contracted route (works are carried out on supporting walls, gaps and overpasses). Works on open roads are also performed (earthworks, works on retaining walls, works on the protection of slopes, etc).