Welcome

WE ARE BEMAX

A company that builds Montenegro

Highway Bar – Boljare

Investor:

China Road&Bridge Corporattion d.o.o. Peking, PR China

Status:

Finished

Year:

2015 – 2022

Value of contracted works:

240.000.000 €

Smokovac interchange

Value of contracted works: 28.000.000 €
Start date: April 2019.
Deadline: 16,5 months
Degree of execution of the project:
Smokovac bridge: 100%
Overpass Zlatica: 100%
Underpass Mihaila Ivanovića: 100%
Under pass Dunavska street: 100%
Lane: 100%
Installations on lane: 100%
Asphalt work: 100%
Equipment on lane: 100%

Suka Tunnel

Value of contracted works: 8.500.000 €
Start date: July 2017.
Deadline: 15 months
Tunel length, both lanes: 1.290,00 m
Degree of execution of the project:
Tunel excavation: completed 14.05.2018.
Concrete and reinforced concrete works: 100%
Tunnel drainage : 100%

Vežešnik Tunnel

Value of contracted works: 27.500.000 €
Start date: April 2017.
Deadline: 21 month
Tunel length: 4.845,00 m
Degree of execution of the project:
Tunel excavation: completed 22.08.2018.
Concrete and reinforced concrete works: 100%
Tunnel drainage : 100%

Open lane (LK 0+000 – LK 6+440,00; RK 0+000 – RK 6+435)

Value of contracted works: 13.000.000 €
Start date: December 2016.
Deadline:24 months
Route length: 4,56 km (lijeva i desna traka)
Excavations: 390.099,16 m3
Embankments: 804.212,33 m3
Degree of completion of the project:
Excavations: 100%
Embankments: 100%

Gornje Mrke bridge

Value of contracted works: 4.500.000 €
Start date: December 2016.
Deadline: 24 months
Bridge length:
Left bridge: 296,00 m
Right bridge: 296,00 m
Degree of completion of the project: 100%

Mrke Tunnel

Value of contracted works: 11.000.000 €
Start date: decembar 2016 godine
Deadline: 24 months
Tunel length: 1.583,00 metara
Degree of completion of the project:
Tunnel excavation: completed 15.12.2017.
Concrete and reinforced concrete works: 100 %
Tunnel drainage: 100%

Podsekcija 1.4. Concrete works

Value of contracted works: 6.000.000 €
Start date: April 2017.
Deadline: 18 months
Route length: 4.042,16 m
Degree of completion of the project:
Support walls: length 336,00 m – degree of completion 100%
Drains: length 452,00 m – degree of completion 100%
Underpasses: length 185,80 m – degree of completion 100%
Lane drainage: 100%.

Overpass Preljubovica

Value of contracted works: 500.000 €
Start date: August 2017.
Deadline: 10 months
Bridge length: 52,00 m
Degree of completion of the project: 100%

Overpass Kisjelica

Value of contracted works: 500.000 €
Start date: October 2017.
Deadline: 10 months
Bridge length: 52,00 m
Degree of completion of the project: 100%

Pelev brijeg Bridge (part of Pelev brijeg interchange )

Value of contracted works: 1.000.000 €
Start date: March 2018.
Deadline: 10 months
Bridge length: 100,00 m
Degree of completion of the project: 100%

Billing station and maintenance base Pelev brijeg

Value of contracted works: 6.500.000 €
Start date: Jun 2019
Deadline: 24 months
Degree of completion of the project: 100%

Đurićev Laz Bridge

Value of contracted works: 5.000.000 €
Start date: March 2017.
Deadline: 24 months
Bridge length:
Left bridge: 352,00 m
Right bridge: 324,00 m
Degree of completion of the project: 100%

Ratkov Laz Bridge

Value of contracted works: 5.000.000 €
Start date: March 2017.
Deadline: 24 months
Bridge length:
Left bridge: 352,00 m
Right bridge: 324,00 m
Degree of completion of the project: 100%

Open lane (LK 17+311 – LK 19+305; RK 17+330 – RK 19+349)

Value of contracted works: 8.500.000 €
Start date: March 2017.
Deadline: 24 months
Route length: 2,32 km (obije trake)
Excavations: 543.287,27 m3
Embankments: 386.113,00 m3
Degree of completion of the project:
Excavations: 100%
Embankments: 100%

Lutovo Bridge

Value of contracted works: 3.000.000 €
Start date: March 2017.
Deadline: 24 months
Bridge length:
Left bridge: 212,00 m
Right bridge: 128,00 m
Degree of completion of the project: 100%

Vjeternik Tunnel

Value of contracted works: 20.500.000 €
Start date: November 2016.
Deadline: 24 months
Tunel length, both lanes: 2.923,00 metara (half of the tunel we have been contracted for)
Degree of completion of the project:
Tunel excavation: completed 09.07.2018
Concrete and reinforced concrete work 100%
Tunnel drainage: 100%

Suvovara Bridge

Value of contracted works: 4.500.000 €
Start date: July 2017.
Deadline: 18 months
Bridge length:
Left bridge: 184,00 m
Right bridge: 240,00 m
Degree of completion of the project: 100%

Open lane (LK 22+695 – LK 22+730; RK 22+570 – RK 22+735)

Value of contracted works: 3.000.000 €
Start date: November 2016.
Deadline: 24 months
Route length: 203,00 m (both lanes)
Excavation: 26.672,02 m3
Embankments: 1.976,20 m3
Degree of completion of the project:
Excavations: 100%
Embankments: 100%

Krkor Bridge

Value of contracted works: 7.000.000 €
Start date: July 2017.
Deadline: 22 months
Bridge length:
Left bridge: 334,00 m
Right bridge: 290,00 m
Degree of completion of the project: 100%

Open lane (LK 22+730 – LK 24+100; RK 22+735 – RK 24+140)

Value of contracted works: 7.000.000 €
Start date: July 2017.
Deadline: 18 months
Route length: 1,73 km (both lanes)
Excavations: 404,482,35 m3
Embankments: 276.920,64 m3
Degree of completion of the project:
Excavation: 100%
Embankments: 100%

Section 4 – Piles for bridges Jabuka, Preslo, Uvač 4, Tara 2, overpass Preslo, supporting walls

Value of contracted works: 7.000.000 €
Start date: Decembar 2016.
End date: March 2020.
Degree of completion of the project: 100%

Billing station Mataševo

Value of contracted works: 1.000.000 €
Start date: April 2020.
Deadline: 10 months
Degree of completion of the project: 100%

Asphalt

Total investment: 38.500.000 €
Start date: march 2019
Deadline: 23 months
Degree of completion of the project: 100%

  • Section 1 – 100 %
  • Section 2 – 100 %
  • Section 3 – 100 %
  • Section 4 – 100 %

Concrete works are currently being carried out on the entire length of the contracted route (works are carried out on supporting walls, gaps and overpasses). Works on open roads are also performed (earthworks, works on retaining walls, works on the protection of slopes, etc).